This edition of Law Update looks at how technology is changing the legal questions businesses are facing across the region. From AI and deepfakes to cyber incidents, cloud services, data protection and digital assets, our lawyers examine where the risks are emerging and how regulators are responding.
The edition also brings together recent legislative developments and significant court decisions from across the UAE and Saudi Arabia, with a closer look at what they mean in practice for businesses operating in the region.
Construction projects run on schedules, budgets, and specifications, and on the assumption that everyone involved will deliver what they promised, when they promised it. In reality, delays creep in, designs change mid-project, defects surface after installation, and payment disagreements pile up until the relationship between contractor and subcontractor breaks down entirely.
At Al Tamimi & Company, our construction and disputes teams regularly advises developers, main contractors and subcontractors through exactly this kind of breakdown, from the first notice of delay through to expert evidence and judgment. This article sets out, in practical terms, how a construction dispute commonly unfolds in Bahrain, drawing on the dynamics seen in infrastructure and fit-out projects alike, and what parties on either side of the contract can do to protect their position long before the dispute reaches a courtroom.
Construction disputes rarely begin with a single dramatic event. They build, almost always, from the same handful of pressure points, a delay in obtaining permits or access to site that pushes back the entire programme; a change in scope or specification requested mid-project that was never properly priced or documented; defects in completed work that surface during inspection or handover; and, eventually, a disagreement over how much is actually owed once the dust settles. Each of these pressure points on its own is manageable. Combined, and left unaddressed, they escalate into exactly the kind of multi-million-fils dispute that ends up before the courts.
Consider a typical scenario where speed to commissioning is commercially critical. A developer engages a main contractor to build a structural works package for a client, who in turn subcontracts the steelwork, civil foundations and installation to a specialist subcontractor. The subcontract is priced on a lump sum basis, with a tight completion window of around three months from the purchase order date, and staged payments tied to progress, an advance payment, interim payments against completed work, and a retention released on final handover.
From the outset, the project is dogged by delay. The work permit from the site owner does not come through until weeks after the contract is signed. A survey of the site then uncovers a buried electrical cable that has to be relocated before foundation work can begin, adding further weeks to the timeline.
By the time real progress is possible, the original completion date has already slipped by months, through no fault of either contracting party. The real dispute begins when the contractor instructs the subcontractor to redesign the structures, increasing both the cost and the scope of the remaining work. The subcontractor proceeds with the revised design without the contract price being formally amended to reflect it.
As the months pass, the contractor becomes increasingly frustrated with the pace of delivery. Site meetings are held, warning letters are sent, and the subcontractor is reminded, more than once, that continued delay risks having the remaining work handed to someone else at its cost. Quality concerns compound the delay, damaged paint coating, and defective corner welds on completed steel units, all of which require rework before installation can proceed. Eventually, the contractor loses patience, instructs the subcontractor to stop work, and brings in a replacement contractor to finish the job, while reserving the right to deduct the cost of delay and defect rectification from whatever is still owed.
The subcontractor sees the same facts very differently. Its account is that the delays were not its fault at all, but were caused by late permits, the buried cable, and a design change that was never properly priced, along with ongoing indecision from the contractor’s technical consultant. It maintains that it had, in fact, completed roughly two-thirds of the contracted work by the time it was removed from site, that it was owed substantial sums for both the original scope and the additional work generated by the design change, and that being replaced without being paid what it was due caused it real financial loss.
This is the point at which many construction relationships end up in litigation, with each side filing a claim,a the contractor for the cost of delay and rectification, the subcontractor for unpaid work and the value of the scope that was taken away from it before it could finish.
Bahraini courts approach these disputes with a clear starting point, a contractor is expected to deliver the work according to the terms of the contract and, where the contract is silent, according to the ordinary standards and practice of the trade, within a reasonable time given the nature of the work. If the contractor’s work is being carried out defectively or contrary to the contract, the law gives the employer a specific remedy, but only if it is used properly:
The employer must formally warn the contractor in writing, giving it a reasonable opportunity to put things right, before it can either terminate the contract or bring in someone else to finish the job at the original contractor’s expense. Skip that warning step, or give an unreasonably short window to respond, and the employer’s later claim for the cost of replacement work becomes much harder to sustain.
Where a contract specifies a fixed percentage deduction per week of delay, courts have consistently treated that kind of delay damages clause as a valid, pre-agreed measure of compensation. Crucially, the party relying on it does not need to separately prove that it suffered actual loss. The existence of the clause itself is treated as strong evidence that delay causes harm, and the burden shifts to the delayed party to show that the clause should not apply, that the delay was not its fault, or that the amount claimed is excessive.
If there is one lesson construction disputes teach again and again, it is that these cases are rarely decided on legal argument alone. They are decided on the numbers, and the numbers come from technical experts. In a typical case, each party appoints its own expert to inspect the site, review the contract, the purchase order, correspondence and change requests, and produce a detailed account, what was actually built, what it was worth, what delay occurred and who caused it, and what, if anything, remains outstanding on each side. Each expert then prepares and submits a report to the court setting out that party’s position on these issues.
In a scenario like the one above, each expert has to work through several points of disagreement. The contractor and subcontractor each want the delay calculation to start from a different point, depending on who they say caused the early delay. They also disagree on the scope of work, since the project changed mid-stream and the parties dispute what was included in the original price versus what constitutes a chargeable variation. And they disagree on the valuation of work in progress, since an incomplete steel structure sitting half-finished on site does not have an obvious market value until someone actually measures and prices it.
Both sides submit their own expert’s report, each challenging the other’s figures. Witnesses are called to give evidence about site conditions and instructions given verbally that were never properly documented. The final judgment is often a careful netting-off exercise, sums owed to the subcontractor for completed and additional work, set against sums owed to the contractor for delay damages and rectification costs, arriving at a single balance owed by one party to the other.
The practical lesson here is one that applies to every construction project, not just the ones that end up in court, contemporaneous documentation decides these cases. A verbal instruction to change the configuration of a structure, given in a site meeting and never confirmed in writing or priced, becomes a matter of competing witness recollection years later. A written variation order, by contrast, converts that same instruction into a number a court can simply add to the account. The parties who come out of these disputes in the strongest position are invariably the ones who kept a clean, dated record of every instruction, every delay event, every warning letter and every site meeting, because that record is what the expert and the court ultimately rely on when the parties’ own accounts of events diverge.
Our construction and disputes teams supports developers, main contractors and subcontractors at every stage of a project’s life cycle. We draft and negotiate construction contracts, purchase orders and subcontracts to close the gaps that most often generate disputes, from variation and delay mechanisms to defects liability and termination rights. We advise in real time when a project starts to go wrong, helping clients issue the right notices, at the right time, in the right form, to preserve their legal position. And when a dispute does reach litigation or arbitration, we manage the full process, including working closely with technical experts to make sure the numbers that go before the court or tribunal reflect what actually happened on site.
If you are managing a delayed project, facing a dispute over variations or defects, or simply want your construction contracts reviewed before the next project breaks ground, our team is available to discuss your position and the options open to you.