Published: Apr 13, 2020

COVID-19 & Force Majeure:  UAE Maritime Law Focus

Read article in Chinese here.

Following the arrival of COVID-19, amongst the considerations that entities in the UAE have been making is whether contractual obligations could still be performed in light of various restrictions that have been imposed. This article explores how the law of Force Majeure operates in the UAE and legal considerations that parties in the maritime industry could make.

 

The Starting Point

Subject to public policy and statutory provisions, UAE law upholds parties’ freedom of contract. Most contracts would include a force majeure clause, and where such clause is absent, contracting parties may fall back on Article 273 of UAE Federal Law No. 5 of 1985 (the “Civil Code”) to invoke force majeure:

(1) In contracts binding on both parties, if force majeure supervenes which makes the performance of the contract impossible, the corresponding obligation shall cease, and the contract shall be automatically cancelled.

(2) In the case of partial impossibility, that part of the contract which is impossible shall be extinguished, and the same shall apply to temporary impossibility in continuing contracts, and in those two cases it shall be permissible for : the obligee to cancel the contract provided that the obligor is so aware.

 

Establishing Force Majeure

In essence, a Force Majeure is a supervening event rendering impossible the performance of an obligation under an agreement between parties. Whilst courts are not bound to follow the decisions of higher courts, judgments of the UAE’s highest court (the Court of Cassation) are typically followed. Therefore it would be helpful to note that the Court of Cassation had in two judgments mentioned that the Force Majeure must be unforeseeable and unavoidable (Dubai Court of Cassation Judgment No. 101 of 2014 (Civil); and Dubai Court of Cassation Judgment No. 49 of 2014). It follows that a Force Majeure declaration is likely to fail if the underlying contract was entered into when public authorities have been imposing ever stricter restrictions because it was foreseeable that that the obligation(s) would be impossible to perform.

Whilst it is good practice to specify what are force majeure events in an agreement, it is not necessary for the words “natural disaster”, “war”, “disease”, “pandemic”, “epidemic” and the like to be expressly mentioned in a force majeure clause for Force Majeure to be successfully declared or argued in court. The key ingredient is impossibility of performance. Mere hardship does not qualify as Force Majeure.

If Force Majeure under Article 273 of the Civil Code could not be established, the doctrine of Exceptional Circumstances under Article 249 of the Civil Code may be an alternative. Unlike Force Majeure, which concerns impossibility, the Doctrine of Exceptional Circumstances applies to excessively difficult obligations “threatening grave loss”. Also unlike the consequence of successfully establishing Force Majeure (where the party declaring Force Majeure will not need to perform the relevant obligation), the party successfully establishing that exceptional circumstances took place would have its relevant obligation(s) adjusted to a level that the Court opines is reasonable.

 

Force Majeure under DIFC law

Under the laws of the Dubai International Financial Centre (“DIFC”), Force Majeure is implied in Article 82 of DIFC Law No.6 of 2004. If an agreement is governed by DIFC law, non-performance by a party is excused if that party proves that the non-performance was due to an impediment beyond its control and that it could not reasonably be expected to have taken the impediment into account at the time of the conclusion of the contract or to have avoided or overcome it or its consequences. However, a Force Majeure event will not excuse a party where its obligation is a “mere obligation to pay”.

 

Maritime Specifics

Article 273 of the Civil Code as discussed above lays down how Force Majeure operates generally under UAE statutes, and that a successful declaration of Force Majeure may result in cancellation of contracts. However, UAE Federal Law No. 26 of 1981 further specifies certain rights and liabilities of parties in maritime and shipping scenarios concerning Force Majeure, that the latter parties should note.

 

SPECIFIC ISSUE GENERAL POINTS
Payment of Crew Wages
  • Crew is entitled to wages for the days spent working in the services of the relevant vessel until the Force Majeure event took place.
Voyage Charterparties
  • A voyage charterparty shall terminate without compensation required by either of the parties to the other, when a Force Majeure event renders the voyage impossible.
  • A voyage charterparty remains in force without compensation or increase in freight if a force majeure event occurs which temporarily interferes with the vessel’s voyage.
Time Charterparties
  • The hire period runs from the day on which the vessel is placed at the disposal of the charterer, until the occurrence of Force Majeure.
Contracts for the Carriage of Passengers
  • If the passenger is prevented from traveling due to Force Majeure, the contract shall be cancelled on the condition that his/her heirs notify the carrier before the voyage of those facts, failing which, the carrier shall be entitled to receive 25% of the fare.
Towage
  • The towing vessel shall be liable for any damage which it causes to the vessel being towed unless it is established that the damage arose out of Force Majeure.
Collision
  • If a collision between vessels arises from Force Majeure, each vessel shall bear the loss it suffered.

Going Forward

Despite the ongoing restrictions faced by parties in the maritime and logistics sectors, many transactions and operations in these sectors are still continuing. Due to the evolving circumstances, it is suggested that the following be considered to be ahead of the potential hurdles and hiccups:

  1. Review your agreements and determine whether the Force Majeure clause specifies epidemics, pandemics, disease, as Force Majeure events;
  2. Consider how notice is performed as stated in your contracts, or if there are specific requirements for declaring Force Majeure;
  3. If you intend to declare Force Majeure, consider how can any of your losses be mitigated and reduced, and do so without delay;
  4. Concerning “Safe Port” obligations under charterparties, determine whether the load and discharge ports that your vessel calls, have implemented procedures to ensure safety of persons and crew;
  5. Review your charterparties’ Deviation Clause to confirm the right to deviate from agreed route(s), and whether freight and hire clauses were drafted in your favour in situations such as deviation;
  6. In Ship Sale & Purchase transactions, buyers should ensure sellers of ships obtain necessary permits from the respective port for the ship to leave following delivery or closing; and
  7. Familiarise yourself with your insurance policies and claim-making processes.

Also read: Force Majeure Event in the UAE

Al Tamimi & Company’s Transport & Logistics team regularly advises on maritime, shipping, trucking, logistics, and customs matters. For further information please contact Omar Omar (o.omar@tamimi.com) or Gabriel Yuen (g.yuen@tamimi.com)