March 2016
A dream renovation could turn to disaster very easily for any Developer or Contractor. Careful thought and drafting is needed to avoid being caught by common pitfalls.
Scenario 1
A luxury hotel wants to have the foyer and restaurant areas refurbished during its off season. These areas include a shopping arcade which is part of the complex but adjacent to the actual hotel. Work is delayed and falls well behind the programme. The Developer is faced with the prospect of the work having to be done over the peak tourist season which may affect hotel bookings and shop turnover. The Contractor is engaged under a construct only FIDIC Red Book 1999.
If work is delayed from the off season to the peak season the hotel operator will claim against the Developer as will the lessees of the shops, which could be very expensive. If the construction contract is based on FIDIC and is not amended the Developer could not accelerate the Contractor’s work to avoid work in peak season or manage this issue by suspending certain work at certain times (noisy or dusty work).
The construction contract should also ensure that any protocol for work to be a carried out which has been agreed with the operator is imposed on the contractor and that the Contractor does not cause the Developer to breach any lease. It may also be the case that agreements for cooling or other services will be impacted and need to be managed under the construction contract. Importantly the agreed damages for late completion should reflect the potential claims or exclude from the rate claims from tenants and the operator.
Scenario 2
A Contractor is working on a hotel redevelopment. The hotel is operating and there are separate specialised contractors who are doing the entry areas. The foyer art work will be completed earier than the entire project as the hotel is to partly open. The foyer art is fragile and may be damaged by too much vibration. During construction the specialised contractors cause delays due to unloading materials and taking longer than scheduled to complete their work. The contract as in scenario 1 is engaged under a construct only FIDIC Red Book 1999.
The Contractor should look to have amendments to the contract to ensure that it is not responsible for the other contractors working on a shared site and that if the other contractors cause delay then it is not the Contractor’s responsibility. The Contractor should also ensure that it is clear that it will get additional costs it incurs should this happen. It is preferable if there is an agreed protocol for who controls the loading docks and what access and egress is given as well as clarifying who is responsible for safety on shared areas. The limitation of liability clause will need careful review and the Contractor should make sure that any particular conditions do not delete the ‘no liability for consequential loss’ provision, which may expose the Contractor to significant loss should the Contractor disrupt the hotel’s business.
As a Developer you would want to ensure that the Contractor is liable for, and is to coordinate work so as to not cause, damage the artwork. The contract will need to manage the early completion of part of the work and the monitoring of vibrations while work continues. Maybe there should be clear rules to protect hotel guests and to not disturb functions, venues and guests sleeping.
While these scenarios are brief, these types of scenarios are almost always encountered in any hotel renovation project. The scenarios highlight dangers for both the Developer and the Contractor.
Developers should:
Contractors should:
All hotel renovation or addition projects will contain unique risks. These risks should be considered and the agreement on how they are to be managed should be properly documented in the construction contract. It is simply too risky to your business as a Developer or a Contractor to use a standard form and ignore these risks.
To learn more about our services and get the latest legal insights from across the Middle East and North Africa region, click on the link below.
Disclaimer: This chat service should not be relied upon as a substitute for professional advice which takes account of your specific circumstances and any changes in the law and practice. No warranty is made as to the accuracy or completeness of the information provided via this service and no liability is accepted by Al Tamimi & Company Limited, its affiliates, partners or employees for any loss arising as a result of reliance upon the information provided.
Kindly accept the disclaimer to proceed to a live chat.
Thank you for your inquiry. We will connect you to one of our agents now.
Thank you. Which service are you looking for?
Thank you for your interest in working with Al Tamimi & Company. Please click here to view our latest job openings.
Please click here leave a message and we will get back to you shortly.